DIY POOL BUILDING CALCULATIONS

PANEL LINER KITS.webp

DIY Pool Prices

DIY Build Process

EXCAVATION


The excavation process begins once you have checked the site measurements and confirmed those are as per drawings. After the outlines are in place it’s time for the exciting work to begin: making space in your garden for your new pool. When hiring the excavator, hire a compatible dumper as well and make sure that there is enough access to easily get rid of the soil.

​

PREPARATION OF THE POOL BASE

 

Once the excavation process has been completed, you will need to put a layer of MOT type 1 for drainage and also sand if you are installing a one-piece pool. For liner pools, its enough to lay a layer of screed at the bottom, and for tiled pools, you would need to pour a concrete raft.

​

BUILDING POOL WALLS

 

Once the floor is done, you build the walls either with polymer panels or ICF blocks, and then lay concrete to support. The pool fittings and plumbing around the pool also go in at the same time.

​

INSTALLING POOL FINISH

 

The pool liner kit in our liner pools is suitable to be cut and fixed on site, ensuring a snug fit and easily accommodating for steps etc. If it is a tiled pool, put the layer of waterproofing first and then tile.

​

POOL EQUIPMENT INSTALLATION

 

Once the finish is installed, run all plumbing around the pool to the plant room and install the pool filter and pump so that when you start filling up the pool you can start filtering the water as well.

​

BACKFILL AROUND POOL

 

The backfilling stage is crucial to ensuring that your pool stays in place. The space around the pool is gradually backfilled using either a dry concrete mixture or gravel. How you backfill the space around your pool matters, you must simultaneously fill the pool and the gap between its outer layer and the excavated hole. This is to ensure that the pressure being exerted on the walls remains balanced.

Building Material Estimates

EASYPANEL SMALL POOL

Excavation & backfilling plant hire                      £750 per week (max 2 weeks) = £1,500
Concrete, steel & floor screed                                     15 sqm @ £250 per sqm = £3,750
Gravel / Sand for backfilling                                        10 cum @ £100 per cum = £1,000

TOTAL .......................................................................................................£6,250

   

EASYPANEL MEDIUM POOL

Excavation & backfilling plant hire                      £750 per week (max 2 weeks) = £1,500
Concrete, steel & floor screed                                     25 sqm @ £250 per sqm = £6,250
Gravel / Sand for backfilling                                        15 cum @ £100 per cum = £1,500

TOTAL .......................................................................................................£9,250 

​

EASYPANEL LARGE POOL

Excavation & backfilling plant hire                      £750 per week (max 3 weeks) = £2,250
Concrete, steel & floor screed                                    40 sqm @ £250 per sqm = £10,000

Gravel / Sand for backfilling                                        20 cum @ £100 per cum = £2,000
TOTAL ......................................................................................................£14,250 

​

EASYPANEL X-LARGE POOL

Excavation & backfilling plant hire                      £750 per week (max 4 weeks) = £3,000
Concrete, steel & floor screed                                    60 sqm @ £250 per sqm = £15,000
Gravel / Sand for backfilling                                        30 cum @ £100 per cum = £3,000

TOTAL ......................................................................................................£21,000 

​​

*All prices including VAT