At diyswimmingpools we want to ensure that you are given all the
relevant facts relating to the construction and maintenance of a swimming pool. Select an area of interest below by using the links provided

 
Choosing a pool
Building a pool
Maintaning a pool
Pool FAQs
or get started with your swimming pool project & click below to start our fast track system  
Get Started
  Polypool provides a fully comprehensive technical support service.

For more information click below.
Technical Support
     
  Case Studies


The end result has always one to be proud of with Polypool. We have showcased a selecion of case studies to demonstrate how smooth the process can be.

download pdf Click here to download all of our case studies as a printable PDF
Please click below on the relevant case study

Case Study 1
Case Study 2
Case Study 3
Case Study 4
Case Study 5
Case Study 6
Case Study 7
Case Study 8
Case Study 9
Case Study 10
Case Study 11
Case Study 12
Case Study 13
Case Study 14


Inground - 75 system

When Gary Searle first considered owning a swimming pool he had to face a number of decisions. In this case study, we give you an honest and transparent overview of what the typical installation will require. This includes the cost of the pool and equipment as well as the man hours and raw materials required to get the job finished.

In Gary’s own words “ I was at first daunted by the choices I had from the start. I knew I wanted a liner pool as I was aware they were popular in countries like the States and France for example. The next thing I had to decide was the actual method to build the pool shell itself. I simply searched on the Internet for Diy swimming pool kits, which took me to Polypool.

• Dig + Soil removal £890 + VAT using grab lorries via contractor found in yellow pages A&P Pools

• Excavation £470 + VAT for plant (3 tonne mini-digger, mini-dumper for one week)

• Materials for pool £820 + VAT (5 bags of sand, 70 bags of cement, 5 ton of pea-shingle, 20 ton of ballast, 2’ x 1’ batten for hopper, polystyrene for base)

• Labour costs using contractors and network of tradesmen/friends.
7.2m x 3.6m complete kit £9,444.65 inc VAT
Liner fitting £1000 inc VAT
Paving slabs & bricks £150 inc VAT
Decking £1500 inc VAT
Winter cover £354 inc VAT
Boiler + Heat Exchanger £1000 inc VAT

• Man Hours The project took a total of 180 man hours with an average of 2 men on site at any one time. This equates to 10 full working days to complete the project, however this was actually done during spare time & weekends.

• Running costs - 24 x 12 pool, £260 + VAT to run this pool on gas for season (May to October). Concrete or blockwork liner pool would cost a minimum of £600 + VAT to run.

swimming pool swimming pool swimming pool swimming pool
Marking out the excavation

Digging the hole Bottom channel goes down straight on top of the dig Panels placed in bottom channel and walls erected
swimming pool swimming pool swimming pool swimming pool
Step unit is cam locked to the pool shell Pool bottom screeded - note main drains protruding at ground level

Screeded floor completed Behind the pool panels is then backfilled
swimming pool swimming pool swimming pool swimming pool
Pool surround is erected 25mm Polystyrene applied to screeded floor

Completed floor covering Liner is placed at the bottom of the pool
swimming pool swimming pool swimming pool
Liner is locked into place Liner is locked into place Liner is gathered around the corner step unit Project complete!

The system was explained to me along with the fact that I would receive technical support from the company throughout the build. The benefits of the Polypool outweighed any other presented to me by other companies I had contacted about this project. I'm an engineer myself and did spend a lot of time studying the concept of the Polypool system. The first thing that struck me was the way it all went together. It was very straight forward. I employed the services of a few good friends and took my time. Whenever I had some spare time, I would do a little bit more. This whole job was completed mainly at week-ends and evenings. I brought in contractors to excavate, put the panels in, screed the floor and fit the liner. In hindsight I needn't have done that.

The bottom channel system and the panels went in no time and had I known how simple it was I would have done it myself. I was asked to work out how many man-hours the job took and to calculate the overall cost of the pool including the kit, the raw materials and any additional labour supplied by my contractors. I would just like to add that building this pool myself not only saved me a lot of money but also gave me a lot of satisfaction.

The long-term benefit for me is that the running costs are already proving to be far lower than they would have been without the heat retention Polypool offered me. After one season, I estimate that the pool has cost us £500 to run including heating and chemicals etc.

The family have had a lot of fun in and around the pool and it's one of the best things I've ever bought after my house and my car."



swimming pools Site layout planner swimming pools Pool builder swimming pools Special Projects swimming pools Case Studies swimming pools Pool & Water Guidelines swimming pools Technical Support swimming pools FAQs
Terms and conditions partners of CO2 Footprint Calculator Grand Designs Magazine
Homebuilding and Renovating Magazine




All rights reserved. All images copyright Polypool Ltd.
This Polypool website is best viewed on - 1024 x 768 resolution and on the following broswers Internet explorer 5.5+, firefox 1.5+, Safari 2.0+
Flash Player 8 is also required to view parts of this site. Click here to get Flash player

DIYswimmingpools.co.uk | Polypool.co.uk | www.eclearuk.com

Home | About DIY Swimming Pools | Product Range | Pool Gallery | FAQs | Get a Quote | Contact Us